Professional Scrum Master FREE Professional Scrum Master Questions and Answers 2 — Questions and Answers
Question 1: A Scrum Team has been using two-week Sprints but consistently fails to deliver a Done Increment. What should the Scrum Master do first?
- Extend the Sprint length to four weeks
- Help the team identify why they cannot finish work within the Sprint (Correct answer)
- Reduce the number of Product Backlog items selected during Sprint Planning
- Assign fewer team members to each backlog item
Correct answer: Help the team identify why they cannot finish work within the Sprint
The Scrum Master should coach the team to inspect and adapt by identifying root causes before making structural changes.
Question 2: Who is responsible for managing the Sprint Backlog during the Sprint?
- The Scrum Master
- The Product Owner
- The Developers (Correct answer)
- The entire Scrum Team
Correct answer: The Developers
The Developers own the Sprint Backlog and are solely responsible for managing it throughout the Sprint.
Question 3: During Sprint Review, a stakeholder requests a feature that conflicts with the current Product Goal. What is the most appropriate response?
- The Scrum Master rejects the request immediately
- The Product Owner captures the feedback and decides how to order it on the Product Backlog (Correct answer)
- The Developers commit to including it in the next Sprint
- The team votes on whether to accept the request
Correct answer: The Product Owner captures the feedback and decides how to order it on the Product Backlog
The Product Owner is accountable for maximizing value and decides how stakeholder feedback is reflected in the Product Backlog.
Question 4: What is the maximum recommended size of a Scrum Team according to the Scrum Guide?
- 7 people
- 9 people
- 10 people (Correct answer)
- 12 people
Correct answer: 10 people
The Scrum Guide recommends that a Scrum Team is typically 10 or fewer people in total, including the Scrum Master and Product Owner.
Question 5: A Development Team member discovers a critical production bug mid-Sprint. What should happen?
- The bug is automatically added to the current Sprint Backlog
- The Product Owner decides whether it is important enough to bring into the current Sprint (Correct answer)
- The Scrum Master adds it to the next Sprint
- The team stops the Sprint and starts a new one
Correct answer: The Product Owner decides whether it is important enough to bring into the current Sprint
The Product Owner determines priority, and the Developers negotiate scope if the bug needs to enter the current Sprint.
Question 6: Which Scrum event provides the primary opportunity for the Scrum Team to inspect how the last Sprint went with regard to people, relationships, processes, and tools?
- Sprint Review
- Sprint Planning
- Daily Scrum
- Sprint Retrospective (Correct answer)
Correct answer: Sprint Retrospective
The Sprint Retrospective is specifically designed for the Scrum Team to inspect itself and create a plan for improvements.
A Scrum Team has been using two-week Sprints but consistently fails to deliver a Done Increment.
What should the Scrum Master do first?