PMP Integration Management 2 — Questions and Answers
Question 1: A project manager discovers that a critical deliverable will be delayed due to an unexpected technical issue. What should the project manager do FIRST?
- Notify the project sponsor immediately
- Assess the impact on the project schedule and other deliverables (Correct answer)
- Request additional resources from the resource manager
- Issue a change request to extend the project deadline
Correct answer: Assess the impact on the project schedule and other deliverables
The project manager should first assess the full impact of the delay before taking corrective action or escalating.
Question 2: Which document formally authorizes a project and grants the project manager authority to apply organizational resources?
- Project Management Plan
- Project Charter (Correct answer)
- Statement of Work
- Business Case
Correct answer: Project Charter
The Project Charter formally authorizes the project and gives the project manager the authority to use organizational resources.
Question 3: During project execution, the team identifies a better way to achieve a deliverable that differs from the approved plan. What is the correct course of action?
- Implement the change immediately to save time
- Document the change and submit a formal change request (Correct answer)
- Inform the team to proceed without documentation
- Cancel the current approach and restart planning
Correct answer: Document the change and submit a formal change request
Any deviation from the approved plan must go through integrated change control via a formal change request.
Question 4: What is the PRIMARY purpose of the Develop Project Management Plan process?
- To define the project scope in detail
- To create a comprehensive document defining how the project is executed, monitored, and closed (Correct answer)
- To assign roles and responsibilities to team members
- To establish the project budget and schedule baseline
Correct answer: To create a comprehensive document defining how the project is executed, monitored, and closed
The Project Management Plan integrates all subsidiary plans and baselines into a cohesive document guiding project execution.
Question 5: A project manager is closing a project phase. Which activity is MOST important during this process?
- Releasing project team members immediately
- Obtaining formal acceptance of phase deliverables (Correct answer)
- Archiving all project documents in the company database
- Conducting a team performance review
Correct answer: Obtaining formal acceptance of phase deliverables
Formal acceptance of deliverables ensures the phase work meets requirements before proceeding to the next phase.
Question 6: Which of the following BEST describes the role of lessons learned in Integration Management?
- They are documented only at project closure
- They inform future projects and can improve current project performance (Correct answer)
- They are kept confidential within the project team
- They replace the need for a project retrospective
Correct answer: They inform future projects and can improve current project performance
Lessons learned are captured throughout the project and become organizational process assets that benefit current and future projects.
Question 7: A project sponsor requests a major scope addition after the project baseline has been set. What should the project manager do?
- Add the scope immediately since it comes from the sponsor
- Evaluate the impact and process through the Perform Integrated Change Control process (Correct answer)
- Reject the request because the baseline has been set
- Add it to a future project and ignore for now
Correct answer: Evaluate the impact and process through the Perform Integrated Change Control process
All changes, regardless of source, must be evaluated for impact and processed through Perform Integrated Change Control.
A project manager discovers that a critical deliverable will be delayed due to an unexpected technical issue.
What should the project manager do FIRST?