PMP Project Resource Management 1 — Questions and Answers
Question 1: Which process involves identifying and documenting project roles, responsibilities, required skills, and reporting relationships?
- Acquire Resources
- Develop Team
- Plan Resource Management (Correct answer)
- Estimate Activity Resources
Correct answer: Plan Resource Management
Plan Resource Management establishes how to estimate, acquire, manage, and utilize physical and team resources on the project.
Question 2: A project manager uses a RACI chart on their project. What does the 'A' in RACI stand for?
- Authorized
- Accountable (Correct answer)
- Assigned
- Advised
Correct answer: Accountable
In a RACI chart, 'A' stands for Accountable — the single person who owns the outcome and approves the work.
Question 3: Which tool shows when and for how long project team members are needed on specific activities?
- Responsibility assignment matrix
- Resource histogram (Correct answer)
- Organizational chart
- RACI chart
Correct answer: Resource histogram
A resource histogram is a bar chart showing resource usage over time, helping visualize when and how much of each resource is needed.
Question 4: A project manager discovers that a critical team member is over-allocated in week 5. What technique should be used FIRST?
- Fast tracking
- Crashing
- Resource leveling (Correct answer)
- Scope reduction
Correct answer: Resource leveling
Resource leveling adjusts the project schedule to resolve resource over-allocations, often by delaying tasks or redistributing work.
Question 5: Which process involves obtaining team members, facilities, equipment, materials, and other resources needed to complete the project?
- Plan Resource Management
- Estimate Activity Resources
- Acquire Resources (Correct answer)
- Develop Team
Correct answer: Acquire Resources
Acquire Resources is the process of obtaining the human and physical resources identified as necessary for project work.
Question 6: What is the PRIMARY purpose of a resource management plan?
- Track project costs
- Define how resources will be categorized, acquired, managed, and released (Correct answer)
- Create the project schedule
- Identify project risks
Correct answer: Define how resources will be categorized, acquired, managed, and released
The resource management plan provides guidance on how project resources will be categorized, allocated, managed, and eventually released.