PMBOK PMP on PMBOK 7th Edition 2 — Questions and Answers
Question 1: PMBOK 7th Edition shifted from process groups to which primary organizing structure?
- Knowledge areas
- Performance domains (Correct answer)
- Delivery phases
- Work breakdown structures
Correct answer: Performance domains
PMBOK 7th Edition replaced the 10 knowledge areas with 8 project performance domains as its primary organizing structure.
Question 2: Which principle in PMBOK 7th Edition emphasizes adapting governance based on context rather than applying a fixed method?
- Enable change
- Tailor based on context (Correct answer)
- Optimize risk responses
- Focus on value
Correct answer: Tailor based on context
The 'Tailor based on context' principle directs project managers to adapt processes, methods, and artifacts to fit the specific project environment.
Question 3: A project manager notices the team is delivering outputs on time but stakeholders are dissatisfied. Which performance domain is most directly failing?
- Planning
- Stakeholder (Correct answer)
- Team
- Delivery
Correct answer: Stakeholder
The Stakeholder performance domain covers engaging stakeholders to ensure their needs and expectations are met, not just delivering outputs.
Question 4: In PMBOK 7th Edition, what term describes the ongoing, iterative process of assessing project work against goals and making adjustments?
- Progressive elaboration
- Uncertainty management
- Measurement and learning (Correct answer)
- Governance oversight
Correct answer: Measurement and learning
Measurement and learning is the performance domain concerned with collecting data, evaluating results, and using insights to improve project outcomes.
Question 5: Which PMBOK 7th Edition principle states that project teams should maintain ethical conduct and honesty with all stakeholders?
- Demonstrate leadership behaviors
- Be a diligent, respectful, and caring steward (Correct answer)
- Navigate complexity
- Create a collaborative project team environment
Correct answer: Be a diligent, respectful, and caring steward
The stewardship principle encompasses responsibility, integrity, and caring for all internal and external stakeholders.
Question 6: A project uses rolling wave planning, releasing detailed plans for near-term work while keeping future phases at a high level. Which performance domain does this primarily belong to?
- Uncertainty
- Development approach and life cycle
- Planning (Correct answer)
- Delivery
Correct answer: Planning
The Planning performance domain encompasses how project plans are developed, including adaptive techniques like rolling wave planning.
Question 7: PMBOK 7th Edition introduces the concept of a 'project management information system' as an example of what broader category?
- Performance domains
- Models, methods, and artifacts (Correct answer)
- Governance frameworks
- Principle applications
Correct answer: Models, methods, and artifacts
PMBOK 7th Edition groups tools, templates, systems, and processes under the umbrella of models, methods, and artifacts rather than prescribing specific ones.
PMBOK 7th Edition shifted from process groups to which primary organizing structure?