PMBOK Guide 3 โ Questions and Answers
Question 1: According to PMBOK 7th edition, which of the following BEST describes a 'project outcome'?
- A scheduled milestone on the project timeline
- An end result or consequence achieved by the project (Correct answer)
- The collection of all project deliverables
- A documented risk that was avoided
Correct answer: An end result or consequence achieved by the project
An outcome is the end result or consequence of a project, which may be tangible or intangible.
Question 2: The PMBOK Uncertainty Performance Domain primarily addresses which challenge?
- Tracking schedule variances and correcting them
- Identifying, assessing, and responding to uncertainty and risk (Correct answer)
- Managing stakeholder communication during conflict
- Controlling scope creep on fixed-price contracts
Correct answer: Identifying, assessing, and responding to uncertainty and risk
The Uncertainty Performance Domain addresses activities associated with identifying and navigating risk and uncertainty.
Question 3: Which PMBOK 7th edition principle states that practitioners should proactively engage with stakeholders who can impact or be impacted by the project?
- Be a diligent, respectful, and caring steward
- Engage stakeholders (Correct answer)
- Demonstrate leadership behaviors
- Recognize, evaluate, and respond to system interactions
Correct answer: Engage stakeholders
The 'Engage Stakeholders' principle emphasizes meaningful engagement with those who can affect or are affected by the project.
Question 4: In PMBOK 7th edition, what is the purpose of a 'project brief'?
- To capture detailed requirements from all stakeholders
- To provide a high-level summary of the project for authorization or initiation (Correct answer)
- To document lessons learned at project closure
- To outline the resource management plan
Correct answer: To provide a high-level summary of the project for authorization or initiation
A project brief provides sufficient information about a project for leadership to decide whether to authorize it.
Question 5: Which development approach delivers value incrementally through repeated cycles and is best suited for projects with evolving requirements?
- Predictive
- Iterative (Correct answer)
- Hybrid
- Sequential
Correct answer: Iterative
An iterative approach repeats cycles of work to progressively refine and deliver value, accommodating changing requirements.
Question 6: According to PMBOK 7th edition, what distinguishes a 'system for value delivery' from an individual project?
- A system for value delivery includes programs, portfolios, and operations that together achieve strategic goals (Correct answer)
- A system for value delivery is a regulatory framework that governs project approvals
- A system for value delivery is the PMO's governance structure
- A system for value delivery is limited to agile projects only
Correct answer: A system for value delivery includes programs, portfolios, and operations that together achieve strategic goals
The system for value delivery encompasses the portfolio, programs, projects, and operations that together deliver value aligned to strategy.
Question 7: When a project manager applies the principle of 'stewardship,' which behavior BEST demonstrates this?
- Focusing exclusively on delivering the project on time and within budget
- Acting responsibly toward the organization, stakeholders, and society at large (Correct answer)
- Delegating all decisions to the project sponsor
- Prioritizing team satisfaction over project outcomes
Correct answer: Acting responsibly toward the organization, stakeholders, and society at large
Stewardship means acting responsibly and ethically in one's role, considering broader impacts beyond just the immediate project.
According to PMBOK 7th edition, which of the following BEST describes a 'project outcome'?