Part P Testing and Inspection — Questions and Answers
Question 1: According to BS 7671, what is the correct sequence of tests for initial verification of an electrical installation?
- Insulation resistance, continuity, polarity, earth fault loop impedance, RCD
- Continuity of protective conductors, continuity of ring final circuits, insulation resistance, polarity, earth fault loop impedance, RCD operation (Correct answer)
- RCD operation first, then all other tests in any order
- Earth fault loop impedance, RCD, continuity, insulation resistance
Correct answer: Continuity of protective conductors, continuity of ring final circuits, insulation resistance, polarity, earth fault loop impedance, RCD operation
BS 7671 Chapter 64 specifies that dead tests must be completed before live tests for safety. The correct sequence is: (1) continuity of protective conductors, (2) continuity of ring final circuits, (3) insulation resistance, (4) polarity, (5) earth fault loop impedance (live test), (6) prospective fault current, (7) RCD operation, and (8) functional testing.
Question 2: When testing the continuity of a ring final circuit, what is the expected result at the socket furthest from the consumer unit?
- Zero ohms
- Approximately 25% of the end-to-end resistance (r1 + r2)/4 (Correct answer)
- The full end-to-end resistance
- Open circuit
Correct answer: Approximately 25% of the end-to-end resistance (r1 + r2)/4
When the cross-connected method is used (line connected to neutral, neutral to line at the consumer unit end), the reading at any socket on the ring should be approximately (r1 + r2)/4, where r1 is the line conductor resistance and r2 is the CPC resistance. This value should be reasonably consistent at every socket, confirming the ring is continuous and has no interconnections.
Question 3: What test voltage is applied when performing an insulation resistance test on a 230V circuit?
- 230V AC
- 250V DC
- 500V DC (Correct answer)
- 1000V DC
Correct answer: 500V DC
For circuits rated between 50V and 500V (which includes standard 230V domestic circuits), insulation resistance is tested at 500V DC. The test instrument applies this voltage between live conductors and earth, and between live conductors. All equipment should be disconnected or switched off, and electronic devices removed to prevent damage from the test voltage.
Question 4: During an earth fault loop impedance test, the measured Zs value at a 32A Type B MCB protected socket is 1.20Ω. Is this satisfactory?
- Yes — it is below the tabulated maximum of 1.44Ω
- No — the measured value must not exceed 80% of the tabulated value (1.15Ω) to allow for temperature increase (Correct answer)
- No — the value should be below 0.5Ω for all circuits
- Yes — any value below 2Ω is acceptable
Correct answer: No — the measured value must not exceed 80% of the tabulated value (1.15Ω) to allow for temperature increase
While the tabulated maximum Zs for a 32A Type B MCB is 1.44Ω, BS 7671 Regulation 411.4.5 and the IET Guidance Note 3 require that the measured value at ambient temperature must not exceed 80% of the tabulated value to account for conductor resistance increasing with temperature during a fault. 80% of 1.44Ω = 1.15Ω, so 1.20Ω fails.
Question 5: What is the purpose of a prospective fault current (PFC) measurement during initial verification?
- To determine the size of cable needed
- To verify that the breaking capacity of the installed protective devices is adequate to safely interrupt the fault current (Correct answer)
- To calculate the electricity bill
- To test the insulation quality
Correct answer: To verify that the breaking capacity of the installed protective devices is adequate to safely interrupt the fault current
The PFC measurement at the origin of the installation (and at other relevant points) ensures that the fault current the supply can deliver does not exceed the breaking capacity (Icn or Icu) of the installed protective devices. If the PFC exceeds the breaking capacity, the device may fail to interrupt the fault safely, potentially causing an explosion or fire.
Question 6: Which certificate must be issued upon completion of a new domestic electrical installation?
- Minor Electrical Installation Works Certificate
- Electrical Installation Certificate (EIC) with a schedule of inspections and schedule of test results (Correct answer)
- Periodic Inspection Report
- PAT test certificate
Correct answer: Electrical Installation Certificate (EIC) with a schedule of inspections and schedule of test results
A new installation requires a full Electrical Installation Certificate (EIC) which must include: a description of the installation, a schedule of inspections (visual checks), and a schedule of test results. The EIC must be signed by the designer, installer, and the person responsible for inspection and testing (these may be the same person). The model forms are in BS 7671 Appendix 6.
According to BS 7671, what is the correct sequence of tests for initial verification of an electrical installation?