General Contractor License Business and Finance Management 2 — Questions and Answers
Question 1: A contractor's overhead rate is calculated by dividing total overhead costs by which figure?
- Gross revenue
- Direct labor costs (Correct answer)
- Net profit
- Total material costs
Correct answer: Direct labor costs
Overhead rate is calculated by dividing total overhead costs by direct labor costs to allocate indirect expenses to projects.
Question 2: Which financial statement shows a contractor's assets, liabilities, and equity at a specific point in time?
- Income statement
- Cash flow statement
- Balance sheet (Correct answer)
- Work-in-progress schedule
Correct answer: Balance sheet
The balance sheet is a snapshot of financial position at a given date, showing what the company owns versus what it owes.
Question 3: A subcontractor fails to complete work and causes a project delay. Under a typical subcontract agreement, the general contractor may:
- Withhold all future payments permanently
- Back-charge the subcontractor for resulting costs (Correct answer)
- Terminate all subcontracts on the project
- File a mechanics lien against the subcontractor
Correct answer: Back-charge the subcontractor for resulting costs
Back-charges allow the GC to deduct costs incurred due to a subcontractor's default from amounts owed to that subcontractor.
Question 4: What does the term 'accounts receivable turnover' measure in a contracting business?
- How quickly the company pays its suppliers
- How efficiently the company collects money owed to it (Correct answer)
- The ratio of revenue to total assets
- The average cost per project completed
Correct answer: How efficiently the company collects money owed to it
Accounts receivable turnover measures how many times receivables are collected over a period, indicating billing and collection efficiency.
Question 5: A contractor purchases a $120,000 piece of equipment with a 5-year useful life and $0 salvage value. Using straight-line depreciation, the annual depreciation expense is:
- $12,000
- $24,000 (Correct answer)
- $30,000
- $60,000
Correct answer: $24,000
Straight-line depreciation divides cost by useful life: $120,000 ÷ 5 = $24,000 per year.
Question 6: Which type of bond guarantees that a contractor will pay subcontractors and material suppliers on a project?
- Bid bond
- Performance bond
- Payment bond (Correct answer)
- License bond
Correct answer: Payment bond
A payment bond protects subcontractors and suppliers by guaranteeing they will be paid even if the general contractor defaults.
Question 7: When preparing a job cost report, 'cost to complete' refers to:
- Total costs spent on the project to date
- Estimated remaining costs needed to finish the project (Correct answer)
- The original contract price minus profit
- Overhead costs allocated to the job
Correct answer: Estimated remaining costs needed to finish the project
Cost to complete is the projected amount still needed to finish the project, used to forecast final job profitability.
A contractor's overhead rate is calculated by dividing total overhead costs by which figure?