Question 1: UX specialists in the Scrum team are required to attend the Daily Scrum even if they don't always have anything to add.
- False
- True (Correct answer)
Correct answer: True
No specializations are recognized in Scrum. The Daily Scrum must be attended by all Developers, who are required to commit to producing some component of a viable increment each Sprint.
Question 2: What exactly is a cross-functional team?
- Each team member has a specialist skill, and a secondary skill in at least one other area
- All team members can perform any task needed
- The team has all skills needed to turn Product Backlog items into "Done" Increments (Correct answer)
- The team has at least one architect, developer, designer and tester assigned to the team
Correct answer: The team has all skills needed to turn Product Backlog items into "Done" Increments
Cross-functional Scrum Teams are made up of people who have all the abilities required to provide value each Sprint. This does not imply that Scrum requires that members of the team have a variety of job functions.
Question 3: Who keeps an eye on job progress throughout a Sprint?
- The Scrum Master
- The Product Owner
- The Project Manager
- None of the Above (Correct answer)
Correct answer: None of the Above
Managing, carrying out, and keeping an eye on the Sprint plan are the Developers' responsibilities. In the Sprint Backlog, this strategy is made clear.
Question 4: Who has the authority to modify the Sprint Backlog?
- Stakeholders
- The Developers (Correct answer)
- The Scrum Master
- The Product Owner
Correct answer: The Developers
The Scrum Guide states that "The Sprint Backlog is a plan by and for the Developers."
Question 5: The Scrum Team should have broken down the Product Backlog items anticipated to be completed during the following Sprint into all of the tasks that need to be finished and added them to the Sprint Backlog by the conclusion of the Sprint Planning session.
- False (Correct answer)
- True
Correct answer: False
Scrum Teams understand that it is impossible to predict what will happen with complicated tasks. As a result, it is anticipated that modifications to the work to be done during the Sprint would be required.
Question 6: The Scrum framework includes which of the following?
- Definition of Ready
- Velocity
- User Stories
- None of the above (Correct answer)
Correct answer: None of the above
Scrum is a simple framework that may be used to implement a number of procedures, strategies, and approaches, including the usage of user stories and story points.
Question 7: To whom does the Scrum Master need to report?
- The Project Manager
- The Lead Scrum Master
- The Agile Coach
- None of the above (Correct answer)
Correct answer: None of the above
Scrum is a simple framework that aids in producing value by providing adaptable solutions to challenging issues. It offers no guidelines for creating the organizational structure.
UX specialists in the Scrum team are required to attend the Daily Scrum even if they don't always have anything to add.