Free Professional Scrum Master MCQ Questions and Answers — Questions and Answers
Question 1: Which of the following doesn't count as one of Scrum's three pillars?
- Commitment
- Courage
- Focus
- Dignity (Correct answer)
Correct answer: Dignity
Being dignified is crucial, yet Scrum does not include dignity in its list of values. Commitment, focus, openness, respect, and bravery are the five Scrum values.
Question 2: Which of the following does not fall under the definition of a Scrum team role or accountability?
- Scrum Master
- Project manager (Correct answer)
- Developers
- Product owner
Correct answer: Project manager
Product owner, Scrum Master, and developers make up the three roles or accountabilities on a Scrum team. Project manager is not a Scrum position. Project manager is not mentioned in the Scrum Guide.
Question 3: The product backlog is best described by which of the following?
- All the features that need to be developed to improve the project (Correct answer)
- All the use cases that were not completed in the previous Sprint and are now backlogged
- All the features that have been completed
- All the features that developers are currently working on
Correct answer: All the features that need to be developed to improve the project
The Scrum Guide refers to the product backlog as "an emergent, ordered list of what is needed to improve the product." It is a list of all the items that are still in development.
Question 4: Among the following, which is not a Scrum event?
- The sprint retrospective
- The daily standup (Correct answer)
- The sprint review
- Sprint planning
Correct answer: The daily standup
It's a little bit of a trick question. Scrum doesn't use daily standup meetings. Daily standup is a word from extreme programming. People "stand up" to ensure that the status meeting doesn't last too long so they don't have aching feet. The word is ableist since not everyone can stand. Furthermore, avoiding discomfort should not be a motivation for brief meetings. There is a daily scrum event in scrum. It doesn't have a daily standup.
Question 5: The product backlog is ordered and managed by who?
- Scrum Master
- Developers
- Product owner (Correct answer)
- Project manager
Correct answer: Product owner
The product owner is solely responsible for the product backlog. Nobody else organizes or assigns a priority to the items in the product backlog, nor does anyone else manage it.
Question 6: A product backlog item is considered finished in Scrum when:
- It meets the team's "definition of done" (Correct answer)
- The Scrum Master considers it shippable
- It makes it through the sprint review with no objections
- It receives sign-off by the project manager
Correct answer: It meets the team's "definition of done"
The "definition of done" is the only indicator by which a product backlog item's completion is evaluated. when a backlog item for a product satisfies the criteria for being finished. A Scrum increment is made once it is judged complete.
Question 7: According to the Scrum Guide, Scrum is:
- Customizable
- Agile
- Alterable
- Immutable (Correct answer)
Correct answer: Immutable
Scrum is said to be immutable, according to the Scrum Guide. Scrum must thus be used in its totality. You cannot pick and choose whatever components of Scrum you wish to use. That is referred to be an antipattern or SrumBut. At all costs, stay away from them.
Which of the following doesn't count as one of Scrum's three pillars?