CSI Project Delivery Methods 1 — Questions and Answers
Question 1: Which project delivery method involves a single contract for both design and construction?
- Design-bid-build
- Construction management at risk
- Design-build (Correct answer)
- Integrated project delivery
Correct answer: Design-build
Design-build combines design and construction services under one contract, fostering collaboration and reducing conflicts.
Question 2: What is a primary advantage of the design-bid-build method?
- Faster schedule
- Early cost certainty
- Clear separation of roles (Correct answer)
- Guaranteed maximum price
Correct answer: Clear separation of roles
Design-bid-build provides clear separation between design and construction, which can simplify risk management.
Question 3: Which delivery method allows early involvement of the contractor during the design phase?
- Design-bid-build
- Design-build
- Construction Manager at Risk (Correct answer)
- Fast-track
Correct answer: Construction Manager at Risk
Construction Manager at Risk (CMAR) involves the contractor early, which helps with constructability and cost estimates.
Question 4: What defines Integrated Project Delivery (IPD)?
- Fixed-price contract
- Sequential scheduling
- Multiple change orders
- Collaborative, shared risk approach (Correct answer)
Correct answer: Collaborative, shared risk approach
IPD uses a shared risk/reward model with early collaboration among owner, designer, and builder.
Question 5: In which method does the owner hold separate contracts with designer and contractor?
- Design-build
- Construction Manager at Risk
- Design-bid-build (Correct answer)
- Integrated Project Delivery
Correct answer: Design-bid-build
Design-bid-build keeps contracts separate, maintaining independence between design and construction.
Question 6: What is one potential drawback of the design-build method?
- Excessive documentation
- Lack of cost efficiency
- Limited owner design input (Correct answer)
- Longer delivery time
Correct answer: Limited owner design input
With design-build, the owner may have reduced control over design since it's handled by the same team managing construction.
Which project delivery method involves a single contract for both design and construction?