Environmental Compliance Inspector Air Quality and Emissions 2 — Questions and Answers
Question 1: Under the Clean Air Act, what is the primary purpose of a State Implementation Plan (SIP)?
- To fund state air monitoring networks
- To demonstrate how a state will attain and maintain NAAQS (Correct answer)
- To license environmental compliance inspectors
- To regulate interstate shipment of hazardous air pollutants
Correct answer: To demonstrate how a state will attain and maintain NAAQS
A SIP outlines the specific measures a state will use to achieve and maintain National Ambient Air Quality Standards within its borders.
Question 2: Which of the following is classified as a 'criteria pollutant' under the NAAQS framework?
- Benzene
- Mercury
- Particulate matter (PM2.5) (Correct answer)
- Hydrogen sulfide
Correct answer: Particulate matter (PM2.5)
PM2.5 is one of six criteria pollutants for which EPA has established NAAQS; benzene and mercury are regulated as hazardous air pollutants instead.
Question 3: A facility subject to Title V permitting must submit a compliance certification to the permitting authority at least:
- Monthly
- Quarterly
- Annually (Correct answer)
- Every five years
Correct answer: Annually
Title V regulations require sources to submit annual compliance certifications to the permitting authority and EPA.
Question 4: What does the term 'Potential to Emit' (PTE) represent for a stationary source?
- Actual measured emissions over the past year
- Maximum capacity emissions assuming continuous operation with no controls (Correct answer)
- The permitted emission limit set by the state
- Emissions calculated using dispersion modeling
Correct answer: Maximum capacity emissions assuming continuous operation with no controls
PTE is the maximum rate at which a source could emit a pollutant operating at full capacity 24/7 with no add-on controls.
Question 5: During a stack test, Method 9 (EPA Reference Method) is used to measure:
- Sulfur dioxide concentration
- Visible emissions opacity (Correct answer)
- Particulate matter mass loading
- Carbon monoxide levels
Correct answer: Visible emissions opacity
EPA Method 9 is the visual determination of the opacity of emissions from stationary sources, performed by a certified observer.
Question 6: Which program requires facilities that emit 100 tons/year or more of a regulated pollutant to obtain a federal operating permit?
- Title IV Acid Rain Program
- Title V Operating Permit Program (Correct answer)
- New Source Review (NSR)
- National Emission Standards for Hazardous Air Pollutants (NESHAP)
Correct answer: Title V Operating Permit Program
Title V of the Clean Air Act establishes the major source operating permit program for facilities emitting 100 tons/year or more of a regulated pollutant.
Question 7: An inspector observes a boiler at a facility running without its baghouse operational. The most immediate regulatory concern is:
- Failure to maintain equipment logs
- Excess particulate matter emissions violating permit limits (Correct answer)
- Improper fuel storage practices
- Missing stack identification tags
Correct answer: Excess particulate matter emissions violating permit limits
Operating combustion equipment without functioning particulate controls typically results in permit limit exceedances for PM emissions.
Under the Clean Air Act, what is the primary purpose of a State Implementation Plan (SIP)?