DBIA Sectors and Application 3 — Questions and Answers
Question 1: In a military design-build project, which document typically defines the owner's requirements and serves as the basis for DB team proposals?
- Basis of Design (BOD)
- Request for Proposal with Performance Work Statement (PWS) (Correct answer)
- Invitation for Bid (IFB)
- Master Program Document (MPD)
Correct answer: Request for Proposal with Performance Work Statement (PWS)
Military DB solicitations use a Request for Proposal paired with a Performance Work Statement that describes functional outcomes rather than prescriptive specs.
Question 2: The use of design-build in the K-12 education sector is most constrained by which factor?
- Lack of qualified DB teams
- State procurement statutes that may require low-bid selection (Correct answer)
- Absence of design standards for schools
- School board opposition to fast-track delivery
Correct answer: State procurement statutes that may require low-bid selection
Many states have statutory requirements for public school construction that mandate lowest-bid selection, limiting best-value design-build procurement.
Question 3: Which sector frequently uses design-build for 'design-assist' arrangements where key trade contractors join the team early?
- Highway and bridge
- Data centers and mission-critical facilities (Correct answer)
- Single-family housing
- Recreational parks
Correct answer: Data centers and mission-critical facilities
Data center projects routinely use design-assist to bring in mechanical, electrical, and low-voltage specialists early to coordinate complex systems.
Question 4: When a port authority uses design-build to expand container terminal capacity, which technical specialty is most critical to integrate early in design?
- Landscape architecture
- Geostructural and marine civil engineering (Correct answer)
- Interior design
- HVAC engineering
Correct answer: Geostructural and marine civil engineering
Marine and geostructural engineers must evaluate soil conditions, wave loads, and pile design early because these factors drive major cost and schedule decisions.
Question 5: In the oil and gas sector, design-build is sometimes called Engineering, Procurement, and Construction (EPC). What is the EPC contractor's primary responsibility?
- Providing financing for the project
- Designing, procuring materials, and constructing the facility under a single contract (Correct answer)
- Only managing third-party subcontractors
- Obtaining all environmental permits on behalf of the owner
Correct answer: Designing, procuring materials, and constructing the facility under a single contract
An EPC contractor assumes single-source responsibility for design, procurement, and construction, mirroring the design-build model in industrial sectors.
Question 6: Which characteristic makes design-build especially suitable for disaster recovery and emergency infrastructure replacement?
- Lower bonding requirements
- Compressed schedule through overlapping design and construction (Correct answer)
- Fewer inspections required
- Automatic waiver of environmental review
Correct answer: Compressed schedule through overlapping design and construction
Overlapping design and construction phases dramatically compress schedules, which is critical when rapid restoration of infrastructure is needed after a disaster.
Question 7: In the transit sector, a design-build contract for a light rail extension would typically assign which risk to the DB team?
- Ridership demand forecasting
- Utility relocation coordination and delay (Correct answer)
- Federal funding allocation decisions
- Environmental impact statement preparation
Correct answer: Utility relocation coordination and delay
DB contracts in transit typically transfer utility relocation coordination risk to the DB team since it directly affects construction sequence and schedule.
In a military design-build project, which document typically defines the owner's requirements and serves as the basis for DB team proposals?