DBIA Risk Management and Allocation 2 — Questions and Answers
Question 1: In design-build, which risk allocation principle holds that risks should be assigned to the party best able to control and manage them?
- Equitable risk sharing (Correct answer)
- Risk retention doctrine
- Risk-benefit alignment
- Shared savings model
Correct answer: Equitable risk sharing
Equitable risk sharing means risks are allocated to the party best positioned to control, manage, and mitigate them.
Question 2: A design-build contract includes a differing site conditions clause. Which category covers conditions materially different from those indicated in the contract documents?
- Type II conditions
- Type I conditions (Correct answer)
- Force majeure events
- Owner-retained risks
Correct answer: Type I conditions
Type I differing site conditions are those materially different from what is indicated or reasonably inferable from the contract documents.
Question 3: When the design-builder assumes design liability in a lump-sum contract, which insurance product specifically covers errors and omissions in the design?
- General liability insurance
- Builders risk insurance
- Professional liability (E&O) insurance (Correct answer)
- Umbrella liability insurance
Correct answer: Professional liability (E&O) insurance
Professional liability (Errors & Omissions) insurance covers claims arising from design mistakes or negligence by the design-builder.
Question 4: Which risk response strategy involves the design-build team negotiating a contingency allowance within the contract price?
- Risk avoidance
- Risk transfer
- Risk acceptance with active mitigation
- Risk retention (Correct answer)
Correct answer: Risk retention
Risk retention with a contingency allowance means the team accepts known risks and budgets for them rather than eliminating or transferring them.
Question 5: Under DBIA best practices, who is primarily responsible for developing the risk register during the pre-award phase?
- The surety company
- The lead designer only
- The design-build team collaboratively (Correct answer)
- The owner's independent reviewer
Correct answer: The design-build team collaboratively
DBIA best practices emphasize collaborative development of the risk register by the entire design-build team during pre-award.
Question 6: An owner includes a 'no damage for delay' clause in a design-build RFP. What risk does this clause primarily transfer to the design-builder?
- Design defect risk
- Schedule delay cost risk (Correct answer)
- Force majeure risk
- Differing site condition risk
Correct answer: Schedule delay cost risk
A 'no damage for delay' clause transfers the financial risk of schedule delays caused by the owner to the design-builder.
Question 7: In a design-build project, which document best serves as the primary vehicle for defining the boundary between owner-retained risks and design-builder risks?
- The basis of design report
- The project risk register
- The Request for Proposal and resulting contract (Correct answer)
- The geotechnical baseline report
Correct answer: The Request for Proposal and resulting contract
The RFP and resulting contract are the foundational documents that legally define which risks each party retains or assumes.
In design-build, which risk allocation principle holds that risks should be assigned to the party best able to control and manage them?