CRC Cheat Sheet 2026
The 30 highest-yield CRC facts, distilled from real exam questions. Print it, save it as a PDF, or study it here β free, no sign-up.
105 questions
180 min time limit
70.00% to pass
- Under the IRC, carbon monoxide alarms are required in residential units that contain which of the following? β Fuel-burning appliances or an attached garage
- When a contract requires the contractor to obtain an 'assignment of warranties' from subcontractors, this means: β The contractor transfers subcontractor warranty rights to the owner at project completion
- A contractor uses a 'look-ahead schedule' on a residential project. What is the typical time horizon for a look-ahead schedule? β 3β6 weeks
- What document does a contractor use to formally request a variance or deviation from a specific code requirement? β Application for variance or appeal to the Board of Appeals
- Which document provides an owner assurance that the subcontractors and suppliers have been paid, thus reducing lien risk on the property? β Conditional lien waiver
- Which type of contract provides the greatest cost certainty for a residential homeowner? β Fixed-price (lump sum) contract
- An inspector notices that anchor bolts for a mudsill are embedded only 5 inches into the concrete foundation. The IRC requires a minimum embedment of: β 6 inches
- A homeowner requests an addition that was not in the original contract. How should a contractor handle this? β Issue a written change order before starting work
- A residential contractor is required to provide a setback of 5 feet from the side property line. Which document establishes this requirement? β Local zoning ordinance
- When a contractor discovers hidden conditions (e.g., buried tanks) that significantly increase costs, the proper action is to: β Stop work, notify the owner in writing, and negotiate a change order
- What is the OSHA requirement for the maximum weight that a scaffold plank must be able to support without failure? β Four times the intended load
- How can cost overruns be prevented in a construction project? β By regularly tracking expenses and adjusting plans as needed.
- What does a 'proprietary' specification require of a contractor? β A specific manufacturer's product must be used with no substitution
- Which accounting method records income and expenses only when cash is actually received or paid? β Cash basis accounting
- What is the first step in the risk management process? β Identify potential risks through systematic analysis
- A contractor uses the 'square foot method' for a preliminary cost estimate. What is the PRIMARY limitation of this approach? β It ignores local labor and material cost variations
- Under the IRC, what is the minimum R-value required for insulation in an exterior wall in Climate Zone 5? β R-13 + R-5 continuous
- Why is it necessary to follow environmental regulations during construction? β To ensure that the construction is environmentally responsible and sustainable.
- What is the purpose of a plan review in the permitting process? β To verify proposed construction complies with codes before work begins
- Under the IRC, what is the maximum rise allowed for each individual stair riser in residential construction? β 7-3/4 inches
- In blueprint reading, what does the symbol 'ΓΈ' (phi) before a number indicate? β Diameter
- During a schedule update, the contractor finds that actual progress is behind planned progress. This is best expressed as a negative: β Schedule variance (SV)
- When a specification says a product must meet ASTM standards, ASTM refers to: β American Society for Testing and Materials
- Which type of duct insulation is required when supply ducts pass through an unconditioned attic space? β Minimum R-8 insulation per the IECC
- A quality control issue arises when a homeowner reports condensation forming inside double-pane windows on a newly completed home. The most likely cause is: β Failed insulated glass unit (IGU) seals allowing moisture between panes
- Under OSHA's Lead in Construction standard, at what airborne lead concentration must employers implement engineering controls and work practices? β The action level of 30 Β΅g/mΒ³
- Under OSHA standards, what color are safety cans used to store flammable liquids typically required to be? β Red
- What is the primary purpose of quality control inspections? β To verify work meets specified standards and identify deficiencies early
- A Florida CRC contractor must renew their license every how many years? β 2 years
- Which clause in a residential contract limits a contractor's total financial exposure for damages to the amount paid under the contract? β Limitation of liability clause
Turn these facts into recall:
Was this helpful?