CPSM CSPM Project Integration & Scope Management 4 — Questions and Answers
Question 1: Which document traces requirements from their origin through design, development, and testing?
- WBS dictionary
- Requirements traceability matrix (Correct answer)
- Scope baseline
- Project management plan
Correct answer: Requirements traceability matrix
The requirements traceability matrix links each requirement to its origin and tracks it throughout the project lifecycle.
Question 2: During project execution, a technical lead makes a 'minor' design change without submitting a change request. The PM should:
- Accept it since technical decisions belong to the lead
- Retroactively document it as an approved change
- Require a formal change request and reverse the change if denied (Correct answer)
- Escalate to the client immediately
Correct answer: Require a formal change request and reverse the change if denied
All changes—regardless of perceived size—must go through integrated change control to maintain the integrity of the baselines.
Question 3: What is the MAIN output of the Define Scope process?
- Work breakdown structure
- Project scope statement (Correct answer)
- Requirements documentation
- Scope management plan
Correct answer: Project scope statement
The project scope statement is the primary output of Define Scope, providing a detailed description of the project and product scope.
Question 4: A project sponsor asks the PM to fast-track delivery without changing scope. What risk does this introduce?
- Reduced scope creep
- Increased rework due to parallel activities that may create conflicts (Correct answer)
- Lower overall project cost
- Improved stakeholder satisfaction
Correct answer: Increased rework due to parallel activities that may create conflicts
Fast-tracking overlaps sequential activities, increasing the risk of rework when later activities depend on incomplete earlier ones.
Question 5: Which integration management activity ensures that changes to one knowledge area are reflected across all related plans?
- Direct and Manage Project Work
- Perform Integrated Change Control (Correct answer)
- Monitor and Control Project Work
- Develop Project Charter
Correct answer: Perform Integrated Change Control
Perform Integrated Change Control reviews all change requests and coordinates updates across scope, schedule, cost, and other management plans.
Question 6: When is the scope baseline FIRST established?
- During project initiating when the charter is signed
- After the WBS and WBS dictionary are approved as part of project planning (Correct answer)
- During project executing when work packages begin
- After the first deliverable is validated by the customer
Correct answer: After the WBS and WBS dictionary are approved as part of project planning
The scope baseline is established during planning after the scope statement, WBS, and WBS dictionary are approved.
Question 7: A customer verbally approves a completed deliverable but refuses to sign the formal acceptance document. The BEST next step is:
- Mark the deliverable as accepted based on the verbal agreement
- Escalate to the project sponsor to resolve the sign-off issue (Correct answer)
- Re-do the deliverable until the customer signs
- Close the project without formal acceptance
Correct answer: Escalate to the project sponsor to resolve the sign-off issue
Formal written acceptance is required; the PM should escalate to the sponsor to resolve the blockage and obtain the signature.
Which document traces requirements from their origin through design, development, and testing?