CPM Cheat Sheet 2026
The 30 highest-yield CPM facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.
100 questions
120 min time limit
70% to pass
- Which metric represents the amount of work that has been accomplished expressed in terms of the approved budget for that work? → Earned Value (EV)
- In CPM risk management, the contingency reserve is BEST described as: → Budget allocated to address known-unknown risks identified in the risk register
- A project team member raises a concern that the team is skipping required testing steps to meet a deadline. The project manager should: → Investigate the situation and enforce the quality management plan requirements
- Which technology trend is most likely to impact stakeholder communication & reporting in the CPM field in coming years? → Digital tools for enhanced data collection, analysis, and reporting
- What is the primary purpose of a control chart in project quality monitoring? → To determine whether a process is stable and in control
- During risk identification for a CPM project, which technique involves structured brainstorming using a hierarchical decomposition of risk categories? → Risk Breakdown Structure (RBS)
- During project execution, a key team member unexpectedly resigns. What should the project manager do FIRST? → Assess the impact on schedule, cost, and quality before taking action
- A project manager discovers that a subcontractor is not meeting contractual obligations during execution. The BEST response is to: → Document the issue and work with the subcontractor to resolve it per contract terms
- When is it appropriate for a project manager to withhold project information from a stakeholder? → When the stakeholder is not on the approved distribution list for that information
- Which CPM resource management tool shows team member availability and workload over time to assist with resource allocation planning? → Resource histogram
- A project is 50% complete. PV = $500,000, EV = $450,000, AC = $480,000. What is the Schedule Variance (SV)? → -$50,000
- Which of the following best describes a key competency required for performance metrics & kpi analysis in CPM certification? → Critical thinking and evidence-based decision making
- When implementing conflict resolution & mediation practices, what should a CPM professional prioritize first? → Compliance with established standards and protocols
- During project execution, a PM learns that a vendor is using subcontractors not approved in the contract. What is the ethically correct response? → Notify the vendor in writing that it is a contract violation and escalate to procurement
- Which document identifies stakeholders and their influence on the project? → Stakeholder register
- In CPM procurement planning, a 'Time and Materials' contract is MOST appropriate when: → The scope of work cannot be precisely defined upfront
- When should risk management planning ideally begin on a project? → At the start of the planning phase
- Theory X management assumptions, as defined by Douglas McGregor, suggest that employees: → Dislike work and must be closely supervised and controlled
- How does continuing education relate to performance metrics & kpi analysis for CPM certified professionals? → It ensures professionals stay current with evolving standards and best practices
- What is the main goal during project execution? → Deliver project outputs
- In CPM team development, which stage of Tuckman's model is characterized by team members beginning to challenge each other and the project manager's authority? → Storming
- Which planning process ensures that the project will include all the work required — and ONLY the work required — to complete it successfully? → Scope management
- What does 'progressive elaboration' mean in project management? → Developing project details incrementally as more information becomes available
- Which element of a project scope statement describes what the project will NOT deliver? → Project exclusions
- Which quality control tool is used to determine whether a process is stable and operating within predictable limits over time? → Control chart
- Why is it important to identify project constraints during initiation? → To plan better and set realistic expectations
- What is the responsibility of a project manager regarding ethics? → Uphold professional ethics
- A project manager is asked to begin work before a project charter is approved. What is the BEST course of action? → Request formal charter approval before committing resources
- What is the purpose of performance reporting? → Communicate project status
- What is the To-Complete Performance Index (TCPI) used for? → Calculating the cost efficiency needed to meet a financial goal