CPM Cheat Sheet 2026

The 30 highest-yield CPM facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.

100 questions
120 min time limit
70% to pass
  1. Which metric represents the amount of work that has been accomplished expressed in terms of the approved budget for that work? Earned Value (EV)
  2. In CPM risk management, the contingency reserve is BEST described as: Budget allocated to address known-unknown risks identified in the risk register
  3. A project team member raises a concern that the team is skipping required testing steps to meet a deadline. The project manager should: Investigate the situation and enforce the quality management plan requirements
  4. Which technology trend is most likely to impact stakeholder communication & reporting in the CPM field in coming years? Digital tools for enhanced data collection, analysis, and reporting
  5. What is the primary purpose of a control chart in project quality monitoring? To determine whether a process is stable and in control
  6. During risk identification for a CPM project, which technique involves structured brainstorming using a hierarchical decomposition of risk categories? Risk Breakdown Structure (RBS)
  7. During project execution, a key team member unexpectedly resigns. What should the project manager do FIRST? Assess the impact on schedule, cost, and quality before taking action
  8. A project manager discovers that a subcontractor is not meeting contractual obligations during execution. The BEST response is to: Document the issue and work with the subcontractor to resolve it per contract terms
  9. When is it appropriate for a project manager to withhold project information from a stakeholder? When the stakeholder is not on the approved distribution list for that information
  10. Which CPM resource management tool shows team member availability and workload over time to assist with resource allocation planning? Resource histogram
  11. A project is 50% complete. PV = $500,000, EV = $450,000, AC = $480,000. What is the Schedule Variance (SV)? -$50,000
  12. Which of the following best describes a key competency required for performance metrics & kpi analysis in CPM certification? Critical thinking and evidence-based decision making
  13. When implementing conflict resolution & mediation practices, what should a CPM professional prioritize first? Compliance with established standards and protocols
  14. During project execution, a PM learns that a vendor is using subcontractors not approved in the contract. What is the ethically correct response? Notify the vendor in writing that it is a contract violation and escalate to procurement
  15. Which document identifies stakeholders and their influence on the project? Stakeholder register
  16. In CPM procurement planning, a 'Time and Materials' contract is MOST appropriate when: The scope of work cannot be precisely defined upfront
  17. When should risk management planning ideally begin on a project? At the start of the planning phase
  18. Theory X management assumptions, as defined by Douglas McGregor, suggest that employees: Dislike work and must be closely supervised and controlled
  19. How does continuing education relate to performance metrics & kpi analysis for CPM certified professionals? It ensures professionals stay current with evolving standards and best practices
  20. What is the main goal during project execution? Deliver project outputs
  21. In CPM team development, which stage of Tuckman's model is characterized by team members beginning to challenge each other and the project manager's authority? Storming
  22. Which planning process ensures that the project will include all the work required — and ONLY the work required — to complete it successfully? Scope management
  23. What does 'progressive elaboration' mean in project management? Developing project details incrementally as more information becomes available
  24. Which element of a project scope statement describes what the project will NOT deliver? Project exclusions
  25. Which quality control tool is used to determine whether a process is stable and operating within predictable limits over time? Control chart
  26. Why is it important to identify project constraints during initiation? To plan better and set realistic expectations
  27. What is the responsibility of a project manager regarding ethics? Uphold professional ethics
  28. A project manager is asked to begin work before a project charter is approved. What is the BEST course of action? Request formal charter approval before committing resources
  29. What is the purpose of performance reporting? Communicate project status
  30. What is the To-Complete Performance Index (TCPI) used for? Calculating the cost efficiency needed to meet a financial goal