CPE CPE Performance Measurement & Reporting 1 — Questions and Answers
Question 1: Earned Value (EV) in project performance measurement is defined as:
- Actual cost incurred to date
- Budgeted cost of work scheduled
- Budgeted cost of work actually performed (Correct answer)
- Estimated cost at completion
Correct answer: Budgeted cost of work actually performed
EV represents the budget value of completed work, providing an objective measure of physical progress independent of actual spending.
Question 2: A Schedule Performance Index (SPI) of 0.85 indicates that the project is:
- Ahead of schedule
- On schedule
- Behind schedule — only 85 cents of scheduled work completed per dollar planned (Correct answer)
- Over budget
Correct answer: Behind schedule — only 85 cents of scheduled work completed per dollar planned
SPI = EV / PV; a value below 1.0 means less work has been accomplished than was planned, indicating a schedule shortfall.
Question 3: The Estimate at Completion (EAC) formula EAC = BAC / CPI is used when:
- Past cost performance is expected to improve significantly
- Current cost performance is expected to continue for the remainder of the project (Correct answer)
- Only schedule variances are considered
- The project has no remaining work
Correct answer: Current cost performance is expected to continue for the remainder of the project
This EAC formula assumes the cost performance index achieved to date will persist through project completion.
Question 4: Which document formally establishes the Performance Measurement Baseline (PMB) in a CPE-managed project?
- Project Charter
- Approved cost-loaded schedule integrated with the WBS and control accounts (Correct answer)
- Risk Register
- Contractor's invoice
Correct answer: Approved cost-loaded schedule integrated with the WBS and control accounts
The PMB is the time-phased budget baseline created by integrating the WBS, schedule, and budget into measurable control accounts.
Question 5: Look-Ahead schedules in performance measurement are typically prepared for a rolling window of:
- 12 months
- 3–6 weeks (Correct answer)
- 5 years
- 1 day
Correct answer: 3–6 weeks
A 3-to-6-week look-ahead gives field teams actionable near-term work plans while aligning with the master schedule.
Question 6: Which KPI directly measures the efficiency of schedule recovery efforts after a delay event?
- Budget at Completion (BAC)
- Recovery Schedule Efficiency — comparing actual vs. planned recovery milestones (Correct answer)
- Contingency drawdown rate
- Total float at project start
Correct answer: Recovery Schedule Efficiency — comparing actual vs. planned recovery milestones
Tracking actual recovery milestones against the recovery plan measures whether acceleration measures are producing the intended schedule improvements.
Earned Value (EV) in project performance measurement is defined as: