CME Project Management and Legal 2 — Questions and Answers
Question 1: A master electrician is awarded a contract that includes a 'liquidated damages' clause. What does this clause typically specify?
- A predetermined daily penalty for project delays (Correct answer)
- The maximum profit the contractor can earn
- Required insurance coverage amounts
- The bonding requirements for the project
Correct answer: A predetermined daily penalty for project delays
Liquidated damages clauses specify a pre-agreed daily monetary penalty the contractor pays if the project is not completed by the contract deadline.
Question 2: Under OSHA 10 standards, which record-keeping form must employers use to log work-related injuries and illnesses?
- OSHA Form 300 (Correct answer)
- OSHA Form 101
- OSHA Form 200
- OSHA Form 400
Correct answer: OSHA Form 300
OSHA Form 300 (Log of Work-Related Injuries and Illnesses) is the required record-keeping document for tracking workplace incidents.
Question 3: A subcontractor on your electrical project files a mechanic's lien. What is the primary purpose of this lien?
- To secure payment for labor and materials provided (Correct answer)
- To delay project completion legally
- To transfer ownership of the project
- To void the general contractor's license
Correct answer: To secure payment for labor and materials provided
A mechanic's lien gives unpaid contractors or suppliers a legal claim against the property to secure compensation for their work or materials.
Question 4: When performing a cost-benefit analysis for a large electrical project, which factor is classified as a 'sunk cost'?
- Money already spent on design drawings that cannot be recovered (Correct answer)
- Projected labor costs for the next phase
- Expected permit fees
- Estimated equipment rental costs
Correct answer: Money already spent on design drawings that cannot be recovered
Sunk costs are past expenditures that have already been incurred and cannot be recovered, and should not influence future project decisions.
Question 5: Which project scheduling technique identifies the sequence of tasks that determines the minimum project duration?
- Critical Path Method (CPM) (Correct answer)
- Gantt charting
- Resource leveling
- Earned value analysis
Correct answer: Critical Path Method (CPM)
The Critical Path Method identifies the longest sequence of dependent tasks, determining the shortest possible project completion time.
Question 6: A master electrician's company receives a 'Notice to Cure' from a project owner. What must the contractor do?
- Correct the specified deficiencies within the stated timeframe or face contract termination (Correct answer)
- File a counter-claim immediately
- Suspend all work pending legal review
- Transfer the contract to another licensed electrician
Correct answer: Correct the specified deficiencies within the stated timeframe or face contract termination
A Notice to Cure gives the contractor a formal opportunity to fix identified deficiencies; failure to do so within the specified period typically allows the owner to terminate the contract.
Question 7: Which type of bond guarantees that a contractor will complete the project according to contract terms?
- Performance bond (Correct answer)
- Payment bond
- Bid bond
- License bond
Correct answer: Performance bond
A performance bond protects the project owner by guaranteeing the contractor will fulfill all contractual obligations and complete the project.
A master electrician is awarded a contract that includes a 'liquidated damages' clause.
What does this clause typically specify?