CEP CEP Grid Infrastructure & Transmission 1 — Questions and Answers
Question 1: Which U.S. federal agency regulates the interstate transmission of electricity and approves transmission tariffs?
- Environmental Protection Agency (EPA)
- Federal Energy Regulatory Commission (FERC) (Correct answer)
- Department of Energy (DOE)
- North American Electric Reliability Corporation (NERC)
Correct answer: Federal Energy Regulatory Commission (FERC)
FERC regulates interstate electricity transmission, approves open-access transmission tariffs, and oversees wholesale electricity markets.
Question 2: What is a 'congestion charge' in electricity transmission?
- A fee for exceeding contracted transmission capacity
- A cost that arises when transmission constraints prevent lower-cost power from flowing to a delivery point (Correct answer)
- A penalty for curtailing scheduled generation
- A surcharge applied during peak demand hours
Correct answer: A cost that arises when transmission constraints prevent lower-cost power from flowing to a delivery point
Congestion charges reflect the price difference between a generation source and the delivery point when transmission constraints limit power flow, forcing use of more expensive local generation.
Question 3: In LMP (Locational Marginal Pricing) markets, what three components make up the total LMP at any node?
- Energy + capacity + ancillary services
- Energy + congestion + losses (Correct answer)
- Generation + transmission + distribution
- Fuel cost + O&M + profit margin
Correct answer: Energy + congestion + losses
LMP = Energy component (system marginal price) + Congestion component (cost of transmission constraints) + Loss component (cost of electrical losses).
Question 4: What is the role of a Regional Transmission Organization (RTO) in the U.S. electricity market?
- It owns and operates generation assets in its region
- It provides independent management of the high-voltage transmission grid and runs competitive wholesale markets (Correct answer)
- It sets retail electricity rates for end-use customers
- It enforces environmental regulations on power plants
Correct answer: It provides independent management of the high-voltage transmission grid and runs competitive wholesale markets
RTOs independently operate transmission systems, dispatch generation to balance supply and demand, and administer wholesale energy, capacity, and ancillary services markets.
Question 5: Which term describes the maximum amount of electricity that can be reliably transmitted over a transmission path without causing reliability violations?
- Firm transmission capacity
- Available Transfer Capability (ATC) (Correct answer)
- Capacity factor
- Transmission loss factor
Correct answer: Available Transfer Capability (ATC)
Available Transfer Capability (ATC) is the remaining capacity on a transmission path after accounting for existing reservations and reliability margins.
Question 6: A customer purchases electricity in an RTO market and takes delivery at a load node with an LMP of $45/MWh, while the hub LMP is $40/MWh. What does the $5/MWh difference represent?
- A capacity charge for peak demand
- The combined congestion and loss components at that delivery node (Correct answer)
- A distribution tariff surcharge
- The renewable energy premium
Correct answer: The combined congestion and loss components at that delivery node
The difference between a node LMP and the hub LMP represents the congestion and loss components specific to that delivery location.
Which U.S. federal agency regulates the interstate transmission of electricity and approves transmission tariffs?