CEC Cost Databases & Resources 2 — Questions and Answers
Question 1: Which RS Means cost data line item component represents the cost of labor, material, and equipment combined for a specific task?
- Bare cost (Correct answer)
- Total including O&P
- Crew cost
- Unit price
Correct answer: Bare cost
Bare cost in RS Means represents the direct cost of labor, material, and equipment without overhead and profit markups.
Question 2: The BNi Building News cost database is primarily organized by which format?
- MasterFormat divisions (Correct answer)
- UniFormat assemblies
- CSI SectionFormat
- OmniClass tables
Correct answer: MasterFormat divisions
BNi Building News cost data is organized using CSI MasterFormat divisions, consistent with industry-standard specification structure.
Question 3: When using Gordian's RSMeans City Cost Index (CCI), a value below 100 for a location indicates what?
- Costs are higher than the national average
- Costs are lower than the national average (Correct answer)
- The data is outdated
- The location has limited data
Correct answer: Costs are lower than the national average
A CCI value below 100 means that local costs are lower than the national average, which is indexed at 100.
Question 4: Which cost database is specifically designed for heavy civil and infrastructure construction estimating?
- RS Means Building Construction
- RS Means Heavy Construction (Correct answer)
- Sweets Network
- Craftsman National Estimator
Correct answer: RS Means Heavy Construction
RS Means Heavy Construction Cost Data is specifically tailored for highway, bridge, underground utilities, and heavy civil work.
Question 5: In the Craftsman National Construction Estimator, labor costs are typically expressed using which wage basis?
- Union journeyman wages
- Open-shop average wages (Correct answer)
- Prevailing wage rates
- Federal minimum wage
Correct answer: Open-shop average wages
Craftsman's National Construction Estimator primarily uses open-shop (non-union) average wage rates for its labor cost data.
Question 6: What is the primary advantage of using square-foot cost estimating guides like those published by Marshall & Swift?
- They provide exact material quantities
- They allow rapid preliminary cost assessments (Correct answer)
- They include subcontractor bids
- They eliminate the need for location adjustments
Correct answer: They allow rapid preliminary cost assessments
Square-foot estimating guides enable quick preliminary (order-of-magnitude) cost assessments early in the design process when detailed information is unavailable.
Question 7: Which organization publishes the 'Construction Cost Indices' used to track inflation and cost trends in the construction industry?
- Associated General Contractors (AGC)
- Engineering News-Record (ENR) (Correct answer)
- American Institute of Architects (AIA)
- Construction Industry Institute (CII)
Correct answer: Engineering News-Record (ENR)
Engineering News-Record (ENR) publishes widely-used construction cost indices including the Building Cost Index (BCI) and Construction Cost Index (CCI).
Which RS Means cost data line item component represents the cost of labor, material, and equipment combined for a specific task?