CAPM Study Guide 2026

Everything you need to pass the CAPM exam in one place: the exam format, every topic to study, real practice questions with explanations, flashcards, and full-length practice tests. Free, no sign-up needed.

📋 CAPM Exam Format at a Glance

150
Questions
180 min
Time Limit
70.00%
Passing Score

📚 CAPM Topics to Study (162)

✍️ Sample CAPM Questions & Answers

1. How should CAPM professionals handle confidential information related to agile & hybrid methodologies?
Follow established protocols for data protection, access control, and disclosure in accordance with applicable regulations

Confidential information must be handled according to established protocols, regulatory requirements, and professional ethics standards, including proper access control and disclosure procedures.

2. Which term describes the formal transfer of project deliverables to operations or the customer at project closure?
Transition

Transition refers to the formal handover of completed deliverables from the project team to the customer, operations, or support teams during project closure.

3. You're in charge of the HNN Project's project management. To install several of the project's components, your team will require safety training. What is the cost of this training?
Cost of quality

The Cost of Quality (COQ) includes all costs incurred to ensure quality, such as prevention costs and appraisal costs, as well as costs incurred as a result of poor quality. Safety training is a *prevention cost*, as it aims to prevent defects, accidents, or non-conformance by ensuring the team has the necessary skills and knowledge. Therefore, it falls under the umbrella of the cost of quality.

4. When the scope of work is well-defined and risk should be transferred to the seller, which contract type is most appropriate?
Fixed Price Lump Sum (FPLS)

Fixed-price contracts transfer cost risk to the seller and work best when scope is clearly defined and unlikely to change significantly.

5. Activity B has an Early Start of day 5, Early Finish of day 10, Late Start of day 8, and Late Finish of day 13. What is its total float?
3 days

Total float = Late Start − Early Start = 8 − 5 = 3 days (or Late Finish − Early Finish = 13 − 10 = 3 days).

6. What is the term for all work required, and ONLY the work required, to complete the project successfully?
Project Scope

Project scope is defined as all the work required, and only the work required, to complete the project successfully.