CAM Aircraft Maintenance and Facilities 2 — Questions and Answers
Question 1: Under which FAR Part are most business aviation flight departments' maintenance programs for turbine-powered aircraft operated under Part 91 typically structured?
- FAR Part 91 Subpart F inspection program provisions (Correct answer)
- FAR Part 121 continuous airworthiness requirements
- FAR Part 147 maintenance training standards
- FAR Part 139 airport certification rules
Correct answer: FAR Part 91 Subpart F inspection program provisions
Part 91 Subpart F (91.409) allows large and turbine-powered multiengine aircraft to use manufacturer-recommended or approved inspection programs.
Question 2: An aviation manager discovers a mechanic deferred a discrepancy without referencing the Minimum Equipment List. What is the primary risk?
- The aircraft may be operated in an unairworthy condition (Correct answer)
- The mechanic loses inspection authorization automatically
- The hangar insurance policy becomes void
- The FAA must be notified within 24 hours
Correct answer: The aircraft may be operated in an unairworthy condition
Deferring items outside the approved MEL process can render the aircraft unairworthy and expose the operator to regulatory violation.
Question 3: Which document must accompany a major repair or major alteration performed on a U.S.-registered aircraft?
- FAA Form 337 (Correct answer)
- FAA Form 8130-6
- FAA Form 8710-1
- FAA Form 7460-1
Correct answer: FAA Form 337
FAA Form 337 records major repairs and alterations and becomes part of the aircraft's permanent records.
Question 4: When budgeting hangar facility costs, which of the following is typically classified as a fixed cost?
- Hangar lease payments (Correct answer)
- Deicing fluid consumption
- Contract labor for unscheduled repairs
- Parts consumed during inspections
Correct answer: Hangar lease payments
Lease payments remain constant regardless of flight activity, making them a fixed cost.
Question 5: A flight department outsources heavy maintenance to an FAA-certificated repair station. Under which FAR Part is that repair station certificated?
- Part 145 (Correct answer)
- Part 135
- Part 65
- Part 43
Correct answer: Part 145
FAR Part 145 governs the certification and operation of repair stations.
Question 6: What is the primary purpose of a maintenance reliability program in a corporate flight department?
- To track failure trends and adjust maintenance intervals proactively (Correct answer)
- To eliminate the need for scheduled inspections
- To reduce mechanic training requirements
- To satisfy OSHA hangar safety rules
Correct answer: To track failure trends and adjust maintenance intervals proactively
Reliability programs analyze component failure data so maintenance can be optimized before failures occur.
Question 7: Which fire suppression consideration is most critical when designing a hangar that will store fueled turbine aircraft?
- Compliance with NFPA 409 hangar classification requirements (Correct answer)
- Installing residential-grade smoke detectors
- Locating extinguishers only at the main entrance
- Using water-only sprinklers over fuel storage
Correct answer: Compliance with NFPA 409 hangar classification requirements
NFPA 409 sets hangar fire protection standards, including foam suppression requirements based on hangar group classification.
Under which FAR Part are most business aviation flight departments' maintenance programs for turbine-powered aircraft operated under Part 91 typically structured?