Architecture Architectural Design Practice 3 — Questions and Answers
Question 1: A contractor submits a substitution request for a specified product during bidding. Who has the authority to approve it?
- The contractor's supplier
- The subcontractor proposing it
- The architect, typically via addendum with owner concurrence (Correct answer)
- The building official
Correct answer: The architect, typically via addendum with owner concurrence
Substitutions during bidding are evaluated by the architect and, if accepted, communicated to all bidders through an addendum.
Question 2: Which contract structure gives the owner a single point of responsibility for both design and construction?
- Design-build (Correct answer)
- Construction manager as adviser
- Design-bid-build
- Multiple prime contracts
Correct answer: Design-build
In design-build, one entity holds responsibility for both design and construction under a single contract with the owner.
Question 3: An architect's certificate for payment indicates that work has progressed to the level claimed. What does it NOT certify?
- The amount the contractor is entitled to be paid
- That observed work has progressed as stated
- That the contractor has paid its subcontractors (Correct answer)
- That work generally conforms to the contract documents
Correct answer: That the contractor has paid its subcontractors
The architect certifies observed progress and conformance, not how the contractor disburses funds to subcontractors.
Question 4: A building site slopes steeply and lies partially within a 100-year floodplain. Which early design response is most appropriate?
- Ignore the floodplain if flood insurance is purchased
- Place mechanical equipment in a basement
- Regrade the entire floodplain to raise the site
- Elevate occupied floors above the base flood elevation (Correct answer)
Correct answer: Elevate occupied floors above the base flood elevation
Locating occupied space and critical systems above the base flood elevation is the fundamental floodplain design strategy required by code.
Question 5: What is the primary purpose of a project kick-off meeting with consultants at the start of design development?
- Select the general contractor
- Finalize construction details
- Negotiate consultant fee reductions
- Align scope, schedule, and coordination protocols across disciplines (Correct answer)
Correct answer: Align scope, schedule, and coordination protocols across disciplines
Kick-off meetings establish shared expectations for deliverables, schedules, and communication before coordinated work begins.
Question 6: Under standard AIA general conditions, who is responsible for construction means, methods, and jobsite safety?
- The building inspector
- The architect
- The contractor (Correct answer)
- The owner
Correct answer: The contractor
AIA A201 assigns means, methods, techniques, sequences, and safety programs exclusively to the contractor.
Question 7: A client asks the architect to reduce the project budget by 15% after design development approval. Which approach best preserves design intent?
- Deleting required egress stairs
- Reducing structural member sizes below calculated loads
- Uniformly downgrading every material one grade
- Value engineering that prioritizes cuts by impact on program and quality (Correct answer)
Correct answer: Value engineering that prioritizes cuts by impact on program and quality
Systematic value engineering evaluates each potential cut against program needs so essential quality and function are preserved.
A contractor submits a substitution request for a specified product during bidding.
Who has the authority to approve it?