AICP MCQ 5 — Questions and Answers
Question 1: A 'special assessment district' is a financing tool that recovers public infrastructure costs by:
- Charging all property owners in a municipality equally
- Levying fees only on properties that directly benefit from the improvement (Correct answer)
- Issuing general obligation bonds backed by the full faith and credit of the government
- Applying impact fees to new development at the time of building permit
Correct answer: Levying fees only on properties that directly benefit from the improvement
Special assessment districts (also called benefit assessment districts) charge only those property owners who receive a direct, measurable benefit from a specific public improvement.
Question 2: Which of the following describes the primary purpose of a 'variance' in zoning administration?
- To allow a use not permitted in a zoning district
- To grant relief from specific dimensional or physical requirements that cause unique hardship (Correct answer)
- To rezone a parcel to a different land use category
- To approve a project that requires conditions of approval
Correct answer: To grant relief from specific dimensional or physical requirements that cause unique hardship
A variance provides relief from specific development standards (setbacks, height, lot coverage) when strict application would create an undue hardship unique to the property, not a use permit for new uses.
Question 3: The 'multiplier effect' in economic base theory refers to:
- The compounding interest on municipal bonds
- How dollars earned in export industries circulate through the local economy, generating additional jobs and income (Correct answer)
- The relationship between land value and development intensity
- How infrastructure investment multiplies property tax revenue
Correct answer: How dollars earned in export industries circulate through the local economy, generating additional jobs and income
The economic multiplier describes how base-sector (export) income recirculates through local businesses and households, generating secondary employment and income beyond the initial economic activity.
Question 4: Under the Americans with Disabilities Act (ADA), which planning document most directly governs a municipality's obligation to make public facilities accessible?
- General plan accessibility element
- ADA Transition Plan (Correct answer)
- Zoning ordinance handicap parking standards
- Building code accessibility chapter
Correct answer: ADA Transition Plan
The ADA Transition Plan is the required document identifying physical barriers in public facilities and programs, setting timelines and priorities for achieving accessibility compliance.
Question 5: A 'concurrency' requirement in growth management means that:
- Multiple planning agencies must review development applications simultaneously
- Adequate public facilities must be in place, or committed to be in place, concurrent with the impacts of new development (Correct answer)
- Affordable and market-rate housing must be built at the same time
- Environmental review and zoning approvals occur in a single process
Correct answer: Adequate public facilities must be in place, or committed to be in place, concurrent with the impacts of new development
Concurrency management, most prominently required in Florida's growth management law, ensures that infrastructure capacity (roads, schools, utilities) is available to serve development at the time it is needed.
Question 6: Which concept describes the planning practice of designating a permanent boundary to contain urban growth and prevent sprawl into surrounding rural or agricultural lands?
- Greenbelt
- Urban Growth Boundary (UGB) (Correct answer)
- Agricultural preservation easement
- Rural Service Area
Correct answer: Urban Growth Boundary (UGB)
An Urban Growth Boundary (UGB) is a regulatory line separating areas planned for urban development from rural lands, with Portland, Oregon's UGB being the most studied U.S. example.
Question 7: The AICP examination's 'Plan Implementation' domain primarily tests knowledge of:
- How to conduct public participation workshops
- Regulatory tools, capital improvement programming, and development review processes (Correct answer)
- Geographic information systems and mapping techniques
- Economic development incentive programs
Correct answer: Regulatory tools, capital improvement programming, and development review processes
The Plan Implementation domain covers the regulatory mechanisms, financial tools, and administrative processes planners use to carry out adopted plans, including zoning, subdivision regulations, and capital budgeting.
A 'special assessment district' is a financing tool that recovers public infrastructure costs by: